Weston Area Construction Update - Basement Flooding Protection Program

*Information as of July 31, 2020


TEXT VERSION:


Basement Flooding Protection Program Sanitary & Storm Sewer Upgrades and Watermain Replacements in the Weston Area


Contracts: 18ECS-LU-03FP and 18ECS-LU-10FP

Start Date: November 2018

End Date: Winter 2021

*Timeline is subject to change.


Basement Flooding Protection Program work in the Weston area is progressing well and is on schedule for completion in Winter 2021. The majority of work will be complete by the end of 2020. Please find information about what has been completed and what remains on the following pages. Thank you for your patience while we compete this important work.


The following streets have had both construction and restoration completed, but still have

minor inlet control device work with existing road infrastructure:


 Arthur Street

 Ettrick Crescent

 Ellis Avenue

 Pine Street (South of Lawrence Ave West)

 Gibson Street

 Jane Street

 Longview Drive

 Pelmo Crescent

 Speers Avenue

 Snowberry Avenue

Contract 18ECS-LU-03FP


John Street

Work Completed:

 Storm sewer construction

 Sidewalk

 Sod replacement


Remaining Work:

 Watermain replacement 90% complete

 Connection work at Jane Street

 Road resurfacing


Estimated Completion Date:

 Early fall 2020


Patika Avenue

Work Completed:

 Watermain replacement and storm sewer construction


Remaining Work:

 Connection work at Jane Street

 Road resurfacing


Estimated Completion Date:

 Late fall 2020


Portage Avenue

Work Completed:

 Sanitary sewer construction

 Sidewalk

 Sod replacement


Remaining Work:

 Road resurfacing


Estimated Completion Date:

 Early fall 2020


Queens Drive (East of Pine Street)

Work Completed:

 Storm sewer construction

 Sidewalk

 Sod replacement


Remaining Work:

 Road resurfacing


Estimated Completion Date:

 Early fall 2020


Robert Street

Work Completed:

 Storm and sanitary sewer construction

 Sidewalk

 Sod replacement


Remaining Work:

 Road resurfacing


Estimated Completion Date:

 Early fall 2020


Wright Avenue

Work Completed:

 Equipment staging


Remaining Work:

 Sewer construction

 Road resurfacing


Estimated Completion Date:

 Late fall 2020


Contract 18ECS-LU-10FP


Boyd Avenue

Work Completed:

 Partial storm sewer construction and watermain replacement completed


Remaining Work:

 Combined sewer reconstruction Watermain

 Road reconstruction


Estimated Completion Date:

 Spring 2021


Church Street

Work Completed:

 Watermain, storm sewer, sanitary sewer and combined sewer reconstruction


Remaining Work:

 Road reconstruction

 Restoration


Estimated Completion Date:

 Late fall 2020


Cypress Street

Work Completed:

 Sanitary sewer construction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late fall 2020


Edmund Avenue

Work Completed:

 Watermain replacement, storm sewer construction

 Road resurfacing


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Summer 2020


Elm Street

Work Completed:

 Watermain replacement, storm sewer construction


Remaining Work:

 Combined sewer

 Road resurfacing


Estimated Completion Date:

 Spring 2021


Grattan Street

Work Completed:

 Storm and sanitary sewer construction

 Partial road reconstruction


Remaining Work:

 Road resurfacing

 Restoration


Estimated Completion Date:

 Late fall 2020


Joseph Street

Work Completed:

 Storm and sanitary sewer construction

 Road resurfacing and reconstruction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


King Street

Work Completed:

 Combined sewer construction


Remaining Work:

 Storm sewer reconstruction

 Road reconstruction

 Restoration


Estimated Completion Date:

 Late fall 2020


Lamont Avenue

Work Completed:

 Sanitary sewer construction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late fall 2020


Langside Avenue

Work Completed:

 Sanitary sewer construction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


MacDonald Avenue

Work Completed:

 Partial storm sewer construction completed


Remaining Work:

 Storm and combined sewer reconstruction

 Road resurfacing

 Restoration


Estimated Completion Date:

 Late fall 2020


Merrill Avenue

Work Completed:

 Watermain replacement

 Partial road resurfacing


Remaining Work:

 Road resurfacing at Lawrence Avenue


Estimated Completion Date:

 Late Fall 2020


Monklands Avenue

Work Completed:

 Road resurfacing


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


Pellatt Avenue

Work Completed:

 Sanitary sewer reconstruction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


Pine Street

Work Completed:

 Partial storm sewer construction completed


Remaining Work:

 Storm sewer reconstruction

 Road reconstruction


Estimated Completion Date:

 Spring 2021


Queens Drive (West of Pine Street)

Work Completed:

 Storm sewer and combined sewer reconstruction


Remaining Work:

 Road reconstruction


Estimated Completion Date:

 Late fall 2020


Queenslea Avenue

Work Completed:

 Watermain replacement and sanitary sewer construction

 Trench roadway restoration


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


Ralph Street

Work Completed:

 Watermain replacement at Lawrence Avenue


Remaining Work:

 Watermain and combined sewer reconstruction

 Road reconstruction


Estimated Completion Date:

 Spring 2021


Sykes Avenue

Work Completed:

 Storm sewer reconstruction

 Road resurfacing


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


Vimy Avenue

Work Completed:

 Storm sewer reconstruction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


Wadsworth Boulevard

Work Completed:

 Combined sewer reconstruction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


Walwyn Avenue

Work Completed:

 Sanitary sewer reconstruction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


Wendell Avenue

Work Completed:

 Storm and sanitary sewer reconstruction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020


William Street

Work Completed:

 Combined sewer reconstruction


Remaining Work:

 Restoration


Estimated Completion Date:

 Late Fall 2020



IMPORTANT INFORMATION ABOUT COVID AND CONSTRUCTION WORK IN TORONTO

As restrictions on construction have been lifted by the Province of Ontario, City-led infrastructure will continue to proceed. During construction, the contractor is responsible for the Health & Safety on site under the Ontario Occupational Health and Safety Act and is expected to implement COVID-19 mitigation practices. For more information on the City's response to COVID-19 please visit toronto.ca/covid-19.



WHAT TO EXPECT DURING CONSTRUCTION

Work Hours: Work will take place from 7 a.m. to 7 p.m., Monday to Friday, with work after hours and on weekends as required.


Traffic Management: Efforts have been made to manage traffic in the area for the safety of workers, road users and residents. Road users should expect delays and increased traffic on nearby main and side streets. TTC detours on Church Street will resume when road reconstruction from Jane Street to Elm Street begins.


Road and Sidewalk Access: In order to complete the work in a safe manner, there will be road and sidewalk restrictions within the work zone. Access for emergency vehicles will be maintained at all times.


Driveway Access: The contractor will notify you of any temporary restrictions to your driveway access. If your property has two entrances, one entrance will be kept open at all times.


Parking: Parking in the active work zone is not permitted as space is needed for construction equipment and materials. This project will affect on-street parking. If your parked vehicle affects construction work, it will be relocated with no charge to the owner. Please call 416-808-2222 for its location.


Parking Violation Notice: In an effort to reduce ticketing due to construction, the City encourages communities with construction to be patient as neighbours may need to temporarily relocate vehicles. If enforcement is called, enforcement must issue a yellow parking violation notice (ticket). If you receive a yellow notice during this construction work, do the following within 15 days of the notice date: 1) Contact the Field Ambassador using the contact below and give them the yellow notice number. 2) Dispute the parking violation notice online or in person following the process listed on the reverse side of the parking violation notice.

You may use this construction notice as part of the explanation of why the violation should be cancelled. Please note: violation notices cannot be cancelled if vehicles are parked in illegal parking spots (i.e. in front of a fire hydrant or in no parking zones).


Tree Removal: Due to the nature of this project, the City may have to remove street trees from the City's boulevard. If this affects a tree near your property, you will receive a separate notice. The City will plant a replacement tree of at least 60mm in diameter.


Physical Distancing: There are times when contractors need to communicate with homeowners about what is happening on-site. This could be about driveway access, water shut offs, exterior pre-construction inspections, and site restoration work (landscaping, installing pavers etc.). Contractor's staff will be identifiable by their high-visibility clothing.

Where possible, a phone number for a contact person on-site will be provided on notices, to answer questions about work near your property. At other times, the contractor may knock on your door, but will then step away the required distance to discuss the work that is taking place and what can be expected that day. Please practice physical distancing with workers so everyone can remain safe. If you have questions, call the contact provided on this notice.


Restoration: The construction work area will be restored with sod and/or asphalt where required to its initial condition. Interlocking bricks, flagstone on a granular base, or other similar features that are removed from public and private property during construction will be replaced. Lawn seeding and/or laying of sod will be done as needed during ideal growing seasons only - in the spring (April to June) and fall (September to October).



NEED MORE INFORMATION?


If you have questions about the upcoming work, please contact us.


Contracts: 18ECS-LU-03FP and 18ECS-LU-10FP


Field Ambassador: Janet Webster, 416-338-5497, bfpp@toronto.ca (M-F 9AM to 5PM)


Ward 5 Councillor: Councillor Nunziata 416-392-4091, councillor_nunziata@toronto.ca


TTY Hearing Impaired Service: 416-338-0889 (7 Days a week, 8a.m. to 5p.m., closed holidays)


General inquiries: 311


Website: toronto.ca/improvements/ward5.htm


Thank you for your patience. Building a great city takes time. Better infrastructure for all of us is worth the wait.